No petroleum sheens or odors were detected last week at the site of former military installations at Buxton Beach when federal, county and National Park Service representatives visited there.
On Thursday, Army Corps of Engineers headquarters and South Atlantic Division officials visited the Buxton FUDS property in Dare County, along with the Savannah District commander, Formerly Used Defense Sites, or FUDS, Program team and Bay West contractors to check out damage from Hurricane Erin, and plan how to best clean up the site. National Park Service officials and members of the Dare County Board of Commissioners also joined the walkthrough.
Supporter Spotlight
“We are committed to doing everything we can within our authorities to remove petroleum-contaminated soil and groundwater from the property,” said Col. Ron Sturgeon, Savannah District commander. “This project remains a priority of the U.S. Army Corps of Engineers and the Savannah District.”
Officials said that after the storm had passed, about 100 feet of asbestos-cement pipe used for water distribution, storm drains and sewer lines was removed from the site surface and secured for proper disposal. A small remnant of the asbestos pipe remains attached to a sump associated with the former wastewater treatment plant, officials said, and that pipe has been temporarily stabilized and wrapped in place.
In addition to the removal of asbestos pipes as authorized under the FUDS authority because of possible risks, the park service has already moved to clear additional debris left behind by Hurricane Erin, utility workers addressed a downed powerline, and an alternate road is being used to access the site until the county repairs Old Lighthouse Road.
When Hurricane Erin passed by, the team was in the process of awarding a contract for phase two of the interim response action that began Aug. 8.
The team is weighing whether to postpone the comprehensive sampling, because of the interim response action.
Supporter Spotlight
“The comprehensive sampling fieldwork can begin once the Quality Assurance Project Plan (QAPP) is accepted. However, since the recent weather events have created a need for the additional (interim response action) excavations in the project area, that work might hinder sampling efforts,” said Sara Keisler, Savannah District FUDS program manager, in the statement. “Therefore, we’re evaluating the possibility of postponing the sampling efforts, so we can ensure unhindered access to all sampling locations. If we do that, the comprehensive sampling fieldwork won’t start until December or January.”