Reprinted from Island Free Press
The 2.4 mile-long “jug handle” bridge was 75% complete as of Thursday, with a projected opening date of late 2021 or early 2022, according to state Department of Transportation’s resident engineer for the project Pablo Hernandez.
Sponsor Spotlight
Hernandez said during the June 3 update meeting that weather and the upcoming hurricane season could alter the estimated completion date, and that once the bridge that will extend over Pamlico Sound between the southern end of the Pea Island National Wildlife Refuge and Rodanthe is officially open, work will begin on both removing the 2.8-mile section of N.C. 12 that the bridge will bypass, and reinstating a public parking lot on the northern edge of the project.
“Without knowing what the weather impacts are going to be, right now we are still projecting late 2021 or early 2022 for the opening of the new structure,” said Hernandez. “At that time, we will start removing N.C. Highway 12. (There is also a) daytime use parking area that is currently being used as a staging area at the north end of the project. That would also become available to the public.”
Hernandez noted that the timing of the contractor responsible for the paving and curbing of the roundabout and roadway approach to the bridge also played a part in the completion date. This phase of the project was expected to continue in the off-season months, however, the mild weather across the state has kept the contractor focused on other projects.
“The roadway contractor is still dealing with backlog work and other work elsewhere in northeast North Carolina, so at this time, it has not been determined when they will resume that work (at the Jug Handle Bridge),” said Hernandez. “Most likely, it will be in the late fall or possibly early winter… I don’t see that roadway work beginning in the summer, mainly because of high traffic volumes and [guidelines regarding] daytime lane closures.”
Early morning concrete placements will likely resume around the middle of this month, with deck pours starting at 2 or 3 a.m. to avoid the daytime heat. “We have about 20 pours to go, so hopefully we can get those pours (done) with minimum disturbance to the community,” said Hernandez.
Sponsor Spotlight
Crews continue to face challenges at the northern end of the bridge, which has not progressed as quickly as the southern end due to the geology of the area. Several different techniques have been explored over the past few months to ease the piling installation difficulties, such as using a 36” diameter auger to loosen the soil during the pile installation.
“Unfortunately, this has been (an issue) for more than a year now,” said Hernandez. (But) the current technique to help ease the pile installation … has shown positive results.”
“The two ends are coming much more into view, and what that equates to is that they are around a half a mile apart from each other… Based on how things have been going, we anticipate pile driving could be complete by early September. That is a date that has some potential movement in it, as we are going into hurricane season, and we could also have a stormy (summer) with rain showers, which also hinders our ability to do work.”
Phase 1 of Cape Hatteras Electric Cooperative’s transmission line relocation is also underway, and includes installing riser poles along the structure, and underground digging on the north end of the project, which is expected to occur later this month. Per the project update, the corresponding work to move the power lines to the new bridge is roughly 75% complete.
As of Thursday, 288 of 388 concrete girders had been set and 90 out of 108 deck spans had been cast — the equivalent of 297 out of 352 pilings.
The jug handle bridge, so dubbed because of its shape when viewed from above, is part of Phase II of the Bonner Bridge Replacement Project, and is the final of the three new bridges on Hatteras Island to be built. The Capt. Richard Etheridge Bridge on Pea Island was completed in spring 2018, and the Bonner Bridge replacement was completed in spring 2019.
Once complete, the bridge will connect the southern portion of the Pea Island National Wildlife Refuge to northern Rodanthe, bypassing the S-turns section of N.C. 12, which is highly susceptible to breaches and ocean overwash during storms.
Updates on the status of the bridge, as well as planned construction activities in the coming month, are available online at https://www.ncdot.gov/projects/nc-12-rodanthe/Pages/planned-construction.aspx.
In addition, more information on the bridge project, which includes project history, maps, documents, and videos, can be found at https://www.ncdot.gov/projects/nc-12-rodanthe/Pages/default.aspx.
The next update meeting is set for Sept. 2, and if all goes well, the meeting will be held both online and in-person in Rodanthe.
This story is provided courtesy of the Island Free Press, a digital newspaper covering Hatteras and Ocracoke islands. Coastal Review Online is partnering with the Free Press to provide readers with more environmental and lifestyle stories of interest along our coast.