From the Outer Banks Voice
NAGS HEAD — The replacement and extension of a 50-year-old stormwater drain pipe into the Atlantic Ocean for the Gallery Row section of Nags Head should be completed by the end of the month.
Sponsor Spotlight
Carolina Marine Structures was awarded an approximately $400,000 contract last year by the N.C. Department of Transportation to remove and replace the original outfall near mile post 10.5 and extend it into the surf.
The work started in the spring but had to be stopped by May 1 due to the start of sea turtle nesting season, although a 15-day extension was granted, according to NCDOT spokesperson Jennifer Heiss.
“They were supposed to resume work at the end of September; however, Joaquin and the neighboring storm prevented them from starting at that time.”
Work on the ‘Red Drum outfall’ resumed about two weeks ago, and should be finished by the end of December, Heiss said.
Four outfall pipes in Nags Head and three in Kill Devil Hills were constructed by NCDOT shortly after the 1962 Ash Wednesday storm to reduce flooding.
Sponsor Spotlight
The Town of Nags Head paid out roughly $1.6 million in 2011 to extend three of the pipes by 50 feet during its beach nourishment project to ensure the pipes would continue to flow properly.
When the project was proposed in 2013, town officials said the pipe had lost some of its length and was so deep under ground that a back hoe had to be used to unclog it.
Flooding was common in the Memorial Avenue and Driftwood Drive areas of Nags Head due to the blockage, especially after heavy rainfall events.